Drawing a well schematic others can trust
Collect the right documents, build casing and completion tables, and produce a schematic that matches what is really in the hole.
The picture
The workflow
Collect the source documents
In: Drilling reports, casing tally, cement reports, completion reportOut: A list of documents with dates
Start from the final well report, then add every workover or intervention after it. The latest document that touched a piece of equipment is the one to trust.
Build the casing table
In: Casing tally and drilling reportsOut: A table of each string: size, weight, grade, top, shoe
List every string from the conductor down to the production casing or liner: outer diameter, weight, grade, top depth and shoe depth. Write down whether each depth is measured depth (MD) or true vertical depth (TVD).
Add hole sizes and cement
In: Cement reports, bond logsOut: Cement tops and hole sizes behind each string
Show the hole size drilled for each section and the top of cement behind each casing. If the cement top is estimated rather than confirmed by a log, say so.
Add the completion
In: Completion report and workover reportsOut: Tubing, packer, valves and perforations at their depths
Add tubing (size and depth), packer, safety valve, nipples, sliding sleeves, and the perforated intervals with their status: open, squeezed or isolated by a plug.
Check it against itself
In: The finished table and drawingOut: A schematic with no contradictions
Check that depths increase in order, that tubing fits inside the casing with room to pass tools, and that each perforation sits inside a cemented string. Mark anything you could not confirm.
What you hand over
A schematic plus an equipment table, each item with its depth, size, source document and date.
Background
What a schematic is for
A well schematic is a drawing of what is in the well and where. Drilling, production, reservoir and well-integrity teams all use it, and many decisions are based on it: whether a tool will pass, where to perforate, whether a barrier is in place.
A schematic is only useful if people can trust it. That trust comes from the table behind the drawing: every item has a depth, a size, a source and a date.
Work from the table, not the picture
Build the equipment table first and generate the drawing from it. If you draw first and add numbers later, small contradictions creep in, and they are hard to see in a picture.
Say what you do not know
If a cement top is estimated, or a depth comes from a plan rather than a report, mark it. An honest gap in the schematic is safer than a confident guess.
Common mistakes
- Mixing MD and TVD in the same table.
- Drawing the well as planned rather than as built.
- Leaving out workovers, so the schematic shows equipment that was pulled years ago.
- Forgetting plugs, fish and abandoned perforations.
- Not recording the source and date, so nobody knows how far to trust the drawing.
Check yourself
Try this workflow in SchemaTech
Draw well schematics, with AI-assisted reading of well documents.
Prefer a walkthrough? Request a guided demo. Studying? See the student discount.
Next workflow: Reading a pressure build-up test